 Swati Lock System
 
Swati Cuplock System Scaffolding

CANTILEVER FRAME
AVAILABLE SIZES:
L : 1.5M L : 1.0M
CANTILEVER BEAM FRAME
AVAILABLE SIZES:
L : 1.5M L : 1.0M
INTERNAL BEAM BRACKET
AVAILABLE SIZES:
L : 1.5M L : 1.0M
 
   Assembly of decking on Cuplock Scaffolding

Space out socket bases and stand in jacks if required (plain shank at top). Assemble a standard on a jack and two ledgers at right angles in a lower cup of this standard. Drop the upper cup of the joint over the two blade ends. Do not tighten. Take a second standard and assemble on another jack, fixing the blade end of the previously assembled ledger into the cup of this standard. Repeat for the third standard to complete a right angled comer.

Add the fourth standard and two more ledgers in a similar manner to complete the assembly of 4 standards and 4 ledgers. Add the upper layer of four ledgers and two braces and assemble the upper jacks and drop head assembles on the top of the completed supporting grid. Finally, add the primary beams and infills in the completed support structures and as grids are completed, tighten all joints.

 

Adjacent supporting grids may be added in a similar way and primary beams and infills added until the required area is completed.

DISMANTLING PROCEDURE
Dismantling follows the same procedure whether the techniques of 'early striking' are followed or not.

The advantages of early striking is that the primary beams and infills may be removed while the concrete soffit remainssupported and completely undisturbed during it's curing period. The primary beams and infills may therefore be re-used this time, thus gaining further concrete production with only and additional set of supporting components.

Primary beams and infills may be removed by striking the drophead wedge. While the primary head of the drophead remains in contact with the concrete, the striking of the wedge allows the beams to drop about 115mm only giving sufficient clearance for the removal of the infills.

Whether the advantages of 'early striking' are taken or not, complete safety in dismanting operations is ensured as primary beams and infills cannot fall to the ground but after striking, must be removed manually.

To assemble Decking on Swati Cuplock Scaffolding remove the drop head assembly from the jack at one end and connect it to the beam. The completed beam with its drop head can now be raised and dropped over the jack."
 

UP POSITION

DOWN POSITION

 

 